Third Quarter Letter to Shareholders

November 18, 2005
To Our Shareholders:

It is my distinct pleasure to report to you that Minera Andes has reached -- and is moving beyond -- an important milestone in its progress towards gold and silver production. We have released a positive feasibility study that shows our Huevos Verdes/San José high-grade gold/silver project to be profitable. The area covered by the feasibility study represents about 15% of the plus 30 kilometers of vein trend identified on the property. We consider these undeveloped areas the tip of our iceberg.

The project is currently in the permitting process with surface and underground development ongoing at the site in southern Argentina. We now have over 300 people working at the site where we plan to be generating cash flow in early 2007. Here are a few highlights from our feasibility study:

*Proven and probable mineral reserves: 1,160,859 tonnes with an average grade of 7.7 g/t gold and 406 g/t silver
*Gold contained: 288,094 ounces, proven and probable
*Silver contained: 15,229,380 ounces, proven and probable
*Average annual production: 60,633 ounces of gold and 3,119,533 ounces of silver
*Average operating cost: $200 per ounce of gold equivalent
*Construction period: about 14 months

Please see our web site, www.minandes.com, for more detailed information about the feasibility study's findings.

Project Financing

The positive feasibility study is an important step in the process of obtaining bank financing. In the third quarter we completed the first step by securing a letter of intent for bank-provided financing for the Huevos Verdes/San José project. The US$50 million bank loan facility is being made available by a syndicate made up of Standard Bank and Bayerische Hypo und Vereinsbank. The loan facility, to be used by Minera Santa Cruz, the joint-owned company developing the project, was subject to, among other things, obtaining the positive feasibility study. It is anticipated that the funds will be available for drawdown in early 2006 when the final permits are received and construction of the process facility will begin. Throughout the third quarter, additional construction progress was made at Huevos Verdes/San José. More than 4,300 meters of underground infrastructure have been completed and additional surface structures are under construction. Oregrade mineralization continues to be stockpiled on the surface.

Third Quarter Exploration

In September, Minera Andes reported three new discoveries, all of which have potential to add to the operating life of the Huevos Verdes/San José project. These new blind drill discoveries make up over two kilometers of new and still openended mineralized vein trend, and are indicators of the mining district-size potential of the 99,000-acre San José project area. With additional work, they hold potential to add to the project's resource and reserve base.

Minera Andes, in addition to its skills in finding gold, silver and copper, is also moving on the road to becoming a gold and silver producer. We are excited to report the progress at Huevos Verdes/San José, as the project moves closer to production.

Cordially,

MINERA ANDES INC.
Allen V. Ambrose
President